Tuesday, October 13, 2009

Lagoon #154 Update






10:45AM- The new one-piece solid weir extension has been installed ( I believe it was completed on 10/9) and seems to be a much better installation than the original extension that was constructed using bricks.

Wednesday, July 29, 2009

lagoon #154 Update

3:45PM - I've been informed by one of our consultants that the control structure for this lagoon is a bubbler box on the southwest side of French Garden Lane. However, there is no evidence of any modifications to the weir, which is supposed to be raised 0.2 feet (2.4 inches), at this time.

Monday, July 27, 2009

Lagoon #154 Update.

8:55AM- The ladder is still there and the safety grating is still leaning against the side of the control structure. The slow leak(s) continue.

Friday, July 24, 2009

Lagoon #154 Update




9:05AM- Although a ladder is still at the site, repairing the control structure appears to be completed(?). However, the joint between the top of the old structure and the bottom of the addition to the structure appears to be leaking in a couple of places already. The dark areas just below the light colored cement in the top two photos show the leaking areas. Who knows how long it will be before these leaks become larger and "we're back to square one" with a lagoon that won't hold it's designed water level? This work either doesn't agree with the rework process that was explained to the Phase 5 Lagoon Committee and the Neighbor Representatives back in March/April or Pulte needs to find a better contractor. The grating also needs to be put back on top of the structure.

Wednesday, July 22, 2009

Lagoon #154 Update

8:55AM- No activity at this time.

Tuesday, July 21, 2009

Lagoon #154 Update




8:40AM- It looks like the repair to the control structure may have been completed yesterday. However, IMHO, it doesn't look like a 1st class job to me and, from what I could tell, it surely doesn't seem to correlate to what we were told by Pulte how it would be done:
1. A groove would be cut in the top of the existing structure to allow for sealing material to be applied between it and the addition to the structure, thereby creating a leakproof seal between the existing structure and the addition made to it.
2. For any addition over two bricks high, a form would be built for controlling the addition of new cement to the existing structure.
My observations: the addition is more than two bricks high. The new cement is very rough and it's hard to believe it was applied using forms. The top of the cement is already cracking.
I also noticed a very small leak on the inside of the structure. Was the groove cut and sealing material applied between the old and new cement? How long will it be before the small leak become a major leak?

Thursday, July 16, 2009

Lagoon#154

11:32AM- Pulte has said that their engineers have confirmed the control structure is leaking. Pulte has committed to repair it by Friday 7/24.
(reference Email from Allison Tucker to Jim Lee, et.al. at 10:32AM today)