Friday, October 30, 2009
Thursday, October 29, 2009
Lagoon #175 Update
2:30PM - Rebuilding the embankment on the lagoon's NW corner that couldn't be reached by the excavators.
Tuesday, October 27, 2009
Lagoon #175 Update
Friday, October 23, 2009
Lagoon #175
9:15AM - Excess soil from dredging operation was being taken away using 3 dump trucks. Apparently the excavator couldn't reach the north end of the lagoon because the machine was sinking too far into the mud. Consequently, that end of the lagoon has not been dredged and that end of the embankment has not been built-up to the proper height yet.
Thursday, October 22, 2009
Lagoon #175 Update
8:45AM- The 1st excavator was in operation. The 2nd excavator was just being delivered via truck to this site. Two person survey team was taking readings streetside. Plan is to double-team the excavators to complete this lagoon.
Wednesday, October 21, 2009
Tuesday, October 20, 2009
Lagoon #175 Update
9:15AM- Pump is on site but not installed yet. Rip-Rap overflow weir seems to be completed. No other activity at this time.
Monday, October 19, 2009
Lagoon #175 Update
Friday, October 16, 2009
Lagoon #175 Update
4:00 PM - Small excavator is on site. Landscaping crew had started installing the guard barrier material along the wetland edge boundary earlier today.
Tuesday, October 13, 2009
Lagoon #175 Update
10:30AM- While at another lagoon meeting today with Keith Willis, we bumped into Todd Doupona and he reported that the recent survey of Lagoon #172 showed that it had not been dredged deep enough, so they were planning to do additional dredging to ensure the proper depth. The pump and excavator that was planned to begin work on L-175 will be temporarily diverted back to L-172 in order to complete the work.
Monday, October 12, 2009
Lagoon #175
9:00AM- Preconstruction Meeting with Todd Doupona (Pulte Project Manager), lagoon abutters, and 3 members of the Phase 5 Lagoon Committee. No issues. Todd expected that a pump would be delivered today and dewatering the lagoon might possibly start tomorrow. The water will be pumped into lagoons L-176 and L-183.