Lagoon #157 Update

8:40AM- A second Pump has been installed at the NW corner of Col. T. Heyward and Landing Lane. It's intake hose is in a curb inlet across the street from the curb inlet that the 1st pump is discharging into. Apparently the two curb inlets are connected since the 2nd pump is re-pumping the discharge from the 1st pump into a 3rd curb inlet about 100 yards further up Col. T. Heyward (west of Landing Ln). The 3rd curb inlet then discharges the water from L-157 into L-235, which is on the south side of Col. T. Heyward. I hope this solution works so they can get on with completing the L-157 work.