Wednesday, July 29, 2009

Lagoon #157 Update

8:55AM - The excavator operator was "fired-up" and the operator was waiting for a load of soil to be delivered (it was late). With luck, he'll complete the soil distribution and rough grading today. There's still a lot of water in the lagoon from the recent rain. Both pumps were "off"

11:30 AM - It was reported that the excavator is at work, soil is being delivered, and T&H engineers are currently at the site.