Thursday, August 13, 2009

lagoon #157 Update




8:50Am - Most of the re-sodding has been completed. There is still a small area on the south-west corner that still needs to have sod installed. Two workers were cleaning up the soil dropped in the roadway from the re-sodding process. The Bobcat is still at the site but it looks like they plan to move it elsewhere today. The heavy rain last night has eroded even more of the hydrograss from the embankment. I also did not see any sign of the Enkamat material having been installed on the embankment.