Tuesday, September 15, 2009

Lagoon #178 Update







9:15AM- The landscapers and T&H surveyors were on-site at this time. There were about 10 workers (landscapers + surveyors) plus a supervisor on site at this time. A bobcat was being used to smooth the embankment in preparation for resodding (pallets of sod were on site).


4:00PM - Notice the weir in the top photo. There is an issue concerning the addition that was made to this weir. The precast addition was not tall enough and the contractor added two layers of brick on top of the addition to achieve the correct height. The mortar job was also poorly done. Pulte (Todd Doupona) agreed to have the bricks removed tomorrow and a new precast addition for the correct height ordered (it should take about ten days for delivery). There is also an issue about the lagoon depth. Pulte had the lagoon bottom surveyed again and will be reviewing the data tomorrow to ensure compliance to the plan.