Wednesday, September 23, 2009

Lagoon #178 Update







10:30AM - The landscaping crew were in the process of completing the resodding. They were working on the street side. The lagoon embankment has been resodded. The temporary road for the dump truck access has been removed and the landscaping restored. The berm section that was "cut away' to allow access for the road has been rebuilt and also resodded.

The only equipment on site at this time was the Bobcat plus 4 pallets of sod. Both excavators have been taken away.

I have to say that, looking at this lagoon, even without much water in it yet, it sure looks a lot better than when it was a "rice paddy".